Local & Sovereign AINotes & KnowledgeObservability & MonitoringPassword ManagersWeb AnalyticsTeam ChatSmart HomeNetworking & RoutersVideo ConferencingCloud Storage & SyncPhotos & MediaAPI DevelopmentImage EditingWorkflow Automation & iPaaSDeveloper Tools & ContainersOffice & Productivity SuitesNo-Code DatabasesCode Hosting & Git ForgesProject ManagementEmail Marketing & NewslettersScheduling & BookingError Tracking & Exception MonitoringLog Management & SIEMVPN & PrivacyEmail & Secure MailVector Databases & AI SearchLLM & Agent FrameworksDomains & Web HostingData Removal & PrivacyAuthentication & IdentityHelp Desk & Customer SupportCloud & VPSKubernetes & Container PlatformsEmbedding ModelsPDF & DocumentsAI Coding AssistantsAI Voice & SpeechLLM Observability & EvaluationLLM Gateways & RoutingCloud GPU & AI ComputeCI/CD & build automationData & pipeline orchestrationModel serving & inferenceAI agent frameworksBackend as a serviceSecrets managementFeature flags & experimentationProduct analyticsSearch infrastructureUptime & status monitoringAffiliate & partner platformsVisitor identification & personalisationWikis & internal docsIdentity & access managementData warehouses & analytics enginesCustomer data platformsCRMObject storageBI & dashboardsE-signatureWhiteboards & diagrammingIn-memory data stores & cachingPlatform as a serviceTransactional & bulk emailHeadless CMSDesign & prototypingE-commerce platformsInternal tools & admin panelsManaged databasesForms & surveysFine-Tuning & Model TrainingRAG & Retrieval PlatformsLLM Evaluation & TestingAI Guardrails & Content SafetySpeech Recognition & TranscriptionExperiment Tracking & ML OpsDocument AI & OCRCompliance automation & security posture

About

How we rank & score

Layer 1 · The numbers that decide

Equipment lead times — transformers, switchgear, generators

How long it takes to buy the electrical gear standing between a signed power contract and an energised rack. Measured in weeks from order to delivery.

The number

What it is
How long it takes to buy the electrical gear standing between a signed power contract and an energised rack. Measured in weeks from order to delivery.
Typical values
Power transformers average 128 weeks · generator step-up units 144 weeks · high-capacity units up to 4 years · medium-voltage switchgear, large generators, UPS and transfer switches all 2-4x pre-pandemic norms

Verified 2026-09-09.

The catch

This is the constraint nobody puts in the plan, and it sits downstream of every other one on this page. A four-year interconnection date means nothing if the transformer behind it is a 128-week order you have not placed yet. Prices are up 77% for power transformers and 45% for generator step-up units since 2019, so the delay costs you twice. Gas is not an escape either: GE Vernova reported 116 GW of turbine capacity under contract — 53 GW of backlog plus 63 GW of slot reservations — running into 2029.

What this is powering

A GB200 NVL72 rack draws 120–132 kW and a GB300 pushes 135–200 kW, against a 2026 average rack of about 27 kW. The silicon decision and the power decision are the same decision, made eighteen months apart.

Layer 2 — Silicon · GB200 NVL72 · The 150 W inference option

Others in the numbers that decide

Sources

Macrostack sells nothing at this layer and takes no commission on any option here. That is precisely why this comparison did not exist — everyone qualified to write it sells one of the answers.