macrostack

Layer 1 · head to head

Solar + battery storage vs On-site natural gas turbines

Intermittent and clean against firm and fast. Almost always paired rather than chosen.

Solar + battery storageOn-site natural gas turbines
Lead time18-36 months12-24 months, the fastest firm power available
Capital costFalling fast; BESS is the swing costModerate; turbine supply chains are now the constraint
CarbonNear zero operationalHigh. This is the trade being made.
Maturityprovenproven

Solar + battery storage

The catch: Intermittent. An AI training cluster does not want to stop at dusk, so this is almost never a standalone answer — it is a cost-reducer alongside firm power.

Decides: Excellent at shaving peak cost and emissions. Not a capacity strategy on its own.

On-site natural gas turbines

The catch: It works, it is fast, and it puts your sustainability commitments in direct conflict with your capacity plan. Turbine lead times have themselves stretched as everyone reached the same conclusion.

Decides: The honest bridge. Most 2026-2028 AI capacity that actually energises on schedule will be gas, whatever the announcements say.

What this powers

Want this whole layer as one table?

The power and cooling options on these pages as a single CSV — lead time, capex, carbon, maturity, density supported, PUE, the catch and what each one decides — ready to sort, filter or load into a notebook.

Get the energy table — free for research and evaluation

Four short lines and the download starts at once (CC-BY-NC-4.0, built from these pages the moment you ask). What you type is used only to answer the request and is never sold. Prefer Hugging Face? Request it there.

Using it inside a product, a client report or anything you sell? That needs a commercial licence.

Verified 2026-09-09. No commission on either option.

The Macrostack brief

New swaps, worth your inbox.

A short, occasional email when we add a high-intent alternative or ship a new head-to-head. No spam, no selling your address — unsubscribe in one click.